If you’re a BTO hopeful counting down the days till you get your keys, chances are you’ve come across the term Probable Completion Date (PCD) and wondered what it really means. Is it your actual move-in date? A rough guess? Or just a polite way for HDB to say “Please don’t ask us every month can?”
Here’s the lowdown on what the PCD actually is, how accurate it tends to be, and why sometimes you may have to tahan a bit longer before you get your dream flat.
What exactly is a BTO Probable Completion Date (PCD)?
The PCD is HDB’s best estimate of when your BTO flat will be completed. It’s usually stated as a quarter and year (e.g. Q3 2025), and you’ll see it when you book your flat or sign your Agreement for Lease.
Think of it as HDB saying, “We aim to pass you the keys by this period… IF everything goes smoothly.” It’s not a guarantee, but rather a helpful reference point so you can start planning your life around it—like selling your current home or shopping for that new fridge.
But wait, there’s also the Delivery Possession Date (DPD), which is the legal deadline HDB has to hand over your flat. That one is usually about a year later than the PCD, just in case things don’t go as planned. So, while the PCD is the target, the DPD is more like the last-call.
Can I move in before my BTO project’s PCD?
Short answer: Sometimes, yes!
In normal, non-pandemic times, many BTO projects actually finish before the PCD. That said, don’t bet all your renovation plans on it. Always give yourself buffer time in case things shift.
Will my BTO’s PCD get delayed?
Despite the best planning, delays in BTO construction can still happen. When they do, it usually means waiting an additional 6 to 12 months to collect your keys. Just earlier this year, HDB had to compensate over 1,000 homeowners from Waterway Sunrise II and Anchorvale Village for unprecedented delays that saw these BTO projects handed over more than a year after their PCD.
Image credit: Google
This compensation totalled S$5.5 million, as reported by CNA, and was said to be the “maximum reimbursement” each homeowner was entitled to for the delays. It also marked the first time HDB was unable to hand over BTO flats by their legal contractual deadlines.
This was also thanks to the dreaded big C—its Circuit Breaker, border closures, and safe distancing rules circa 2020 threw a major spanner into BTO timelines for a full two years, causing delays in almost every BTO project launched in 2020 and 2021. As a result, average BTO wait times stretched from 2-4 years to 4-5 years.
Aside from that, delays can also happen for the following reasons:
- Manpower or material shortages: Not enough workers or delays in getting materials (like precast concrete from Malaysia) can hold things up.
- Contractor issues: Sometimes the main contractor might underperform or even fold, requiring HDB to reassign the project to someone else.
- Site challenges: Bad soil, design adjustments, or unexpected issues on the ground can slow progress.
- Weather: Prolonged heavy rain can delay works, though this is less common in Singapore.
How do I keep track of my BTO flat’s progress?
Image credit: Google
Our advice if to keep the My HDBPage as a pinned tab in your browser. You’ll want to log in regularly to:
- View your updated PCD
- See photo updates of your block under construction
- Check for any changes to your timeline
If there’s a delay or update, HDB will reflect it here first. For major updates, you might also get an email, SMS, or physical letter.
When your flat is finally ready, HDB will notify you about your key collection appointment—usually a few weeks in advance. That’s when you know it’s really happening.
TL;DR BTO Probable Completion Date (PCD)—what is it & why is it important?
At the end of the day, your PCD is a helpful heads-up from HDB, not a pinky promise. As with most things in life (and construction), delays can happen—but at least now you’ll know what to expect, how to prep, and how to avoid kena shocked when timelines shift.
Don’t rush to sell or terminate your current home or rental lease until your key collection appointment is officially confirmed. And if you’re planning reno works, be sure to factor in some flexibility—your PCD might shift, and you don’t want to be stuck with a contractor but no keys.
If you’re renting: It’s safer to rent beyond the PCD, not just until it. Treat the PCD like a soft deadline—give yourself a few months’ leeway so you’re not left scrambling if there are delays.
If you’re planning renovations: You can start researching IDs or getting quotes around 3 to 6 months before the PCD, but avoid locking in dates until you receive your key collection appointment.
Read our other articles here:
- Hidden costs that come with buying a BTO
- How to choose the right BTO unit
- Unofficial BTO tips shared by homeowners
Cover image credit: Google, HDB
Drop us your email so you won't miss the latest news.